Short answer: A mansard conversion takes 10 to 16 weeks to build and typically six to nine months from first survey to completion, once design, planning and party wall agreements are included.
How long is the design stage?
Three to four weeks for survey and planning drawings.
How long is planning?
Eight weeks is the target for a householder decision after validation.
What happens between planning and site?
Structural design, building regulations drawings and party wall notices: four to eight weeks, often overlapped with planning to save time.
What are the stages on site?
Scaffold and temporary roof in week one or two; strip-out, steel and floor by week four; mansard frame and party walls by week seven; weathertight by week nine; fit-out to week fourteen or so.
What causes delay?
Late party wall awards, planning conditions that need discharge before starting, and changes made after work begins. Fixing the design before the scaffold goes up is the best protection.